CALTRANS FILLMORE AREA INFORMATION (Scheduled as Night Work):

 

 

The City's Street Resurfacing Project (on B Street, C Street, D Street and Mountain View Streets):

Scheduled starting June 11th for approx. 3 weeks:

-Cold Milling - Wed 6/13

-Dig Outs/Surface Prep- Thurs 6/14-Fri 6/15

-Paving Mon 6/18-Tues 6-19

-Utility lid adjustments - 6/20-6/22

-Traffic Loops - 6/21  - 6/22 (B St and C St)

-Pavement Markings 6/25-6/26

 

Further Info:

-Replace Lanes near A. Street (SR126 and HW 23): delay into July