Central Avenue Storm Drain
Two Week Time-Line
 
     
Monday 3/16/2009   Strip forms from 21' catchbasin on Central Ave and First St. 
    Continue working on 1 1/2" irrigation to center medians.
     
Tuesday 3/17/2009   Excavate 28' catchbasin on Central and First St. Place 
    shoring for catchbasin. Relocate unmarked gas line. Clean up.
     
Wednesday 3/18/2009   Finish excavating 28' catchbasin. Set shoring. Pour floor
    in 21' catchbasin. Install clock in center median.
     
Thursday 3/19/2009   Tie rebar in 28' catchbasin and form catchbasin walls.
    Start clean up on bone yard.
     
Friday 3/20/2009   Form and pour 28' catchbasin. Continue on clean up.
     
Monday 3/23/2009   Strip 28' catchbasin and remove shoring. Start excavating
    storm drain laterals on Central Ave. Install plants in center
    medians. Install drip hose.
     
Tuesday 3/24/2009   Continue to install storm drain laterals on Central Ave.
    Continue installing plants. Start forming catchbasin decks.
     
Wednesday 3/25/2009   Continue to install storm drain laterals on Central Ave. Continue 
    on forming catchbasin decks and possibly pouring them.
     
Thursday 3/26/2009   Continue to install storm drain laterals on Central Ave. Continue 
    on forming catchbasin decks and possibly pouring them.
     
Friday 3/27/2009   Continue to install storm drain laterals on Central Ave. Continue 
    on forming catchbasin decks and possibly pouring them.

 

Rick Henderson
Lash Construction, Inc.  
General Contractor
805-963-3553
Doug Hack
Boyle Engineering
805-340-7434
Bill Bartels
City of Fillmore
805-990-5946

 

     

 

 
 
Questions or Comments about this Website?
Email pmaynard@ci.fillmore.ca.us
© City of Fillmore 2006